
Reacting to the Flood
Report from Michael Gomoll
Chi/Cor Information Management, Inc.
In 1899 the city of Chicago started work on a series of interconnecting tunnels located approximately forty feet beneath street level.
This series of tunnels ran below the Chicago River and underneath the Chicago business district, simply known as The Loop. The
tunnels housed a series of railroad tracks that were used to haul coal and to remove ashes from the many office buildings in the
downtown area. The underground system served Chicago well through the 1940s when other power sources replaced the coal
furnaces. These tunnels went forgotten until April 13th, 1992.
Construction workers had been working along the Chicago River for some time. One of the projects included placing support pillars
into the Chicago River bottom.
It is theorized that during the placement of one of these pillars, a portion of the turn-of-the-century coal delivery system was
damaged. A hole the size of a large automobile formed in the bottom of the river and punctured the tunnel ceiling.
Exactly when the rupture took place is unclear, but on the morning of Monday April 13th several Loop office buildings began to
report significant amounts of water in basement and sub-basement facilities. The flooding was caused by massive amounts of river
water pouring into the maze of underground tunnels. The tunnels led directly into the basements of many of the older Loop
buildings.
Marshall Fields flagship store, located on State Street in the heart of the loop, reported flooding in sub-basements two and three
with water levels reaching 40 feet. With heating and electrical systems located in these basement areas, not to mention a substantial
amount of valuable inventory, the threat was significant.
Most of the City and County governmental buildings are also located in the Loop. As with the Marshall Field's building, the
City/County utilities were threatened by extensive flooding. Valuable assets were also in jeopardy, but in this case the assets took the
form of valuable government records. The records existed in hard copy and microfiche form and contained a wealth of historical
information about the nations third largest city.
Chicagos financial district, including the Chicago Board of Trade and Chicago Mercantile Exchange, was also threatened by the
torrent of water. The threat of the flooding came not so much from the water itself, but from the impact the flood could have on the
extensive electrical and computer networks.
It doesnt require an advance degree in electrical engineering to imagine the potential safety risks to office buildings, some over 100
stories high with thousands of tenants, if the electrical system is compromised. By mid-day, the entire loop business district was
evacuated.
CHI/COR Information Managements corporate headquarters is located in the heart of the loop and was also affected by the
flooding. Located in the southwest corner of the loop, adjacent to the Sears Tower, its offices were on the outer edge of the
affected area.
The first order of business for the Executive Committee was to determine what business processes were threatened, and based
upon a business impact analysis, initiate the appropriate recovery steps. The Executive committee highlighted the following recovery
processes:
1) Evaluate The Threat To Personnel
2) Activate Customer Support Network Procedures
3) Prepare Off-Site Facilities
4) Back-up And Secure Information Systems
Here is how each of these areas was addressed.
Evaluate The Threat To Personnel
It was determined that the threat to personal safety was minimal at the time of disaster declaration, though it was decided that
eventually complete evacuation would be a necessity.
The buildings elevator system was scheduled to be shut down by 1:30 p.m. To help avoid a bottleneck at 1:25, all non-essential
personnel were evacuated in stages as their recovery functions were completed.
All employees were kept informed of evacuation alternatives and timeframes. By following the predefined evacuation procedures
and routes, all non-essential personnel were evacuated well before the 1:30 deadline.
This orderly evacuation helped make the subsequent evacuation of the emergency staff quick and efficient when the time came.
Activate Customer Support Network Procedures
After all personal safety issues were addressed, the Customer Support Team went into action. Their first order of business was to
re-route all customer support lines to a cellular telephone network. Once these cellular channels were in place, the Customer Support
Team worked in tandem with the Off-site Facilities Team to ensure that support personnel would have continuous access to their
various support tools and databases.
Prepare Off-Site Facilities
Our plan called for the availability of personal computers at several off-site locations for members of the support and development
teams. Many support and development personnel have access to PCs at home. The Customer Support plan called for the staggered
dispersion of personnel to off-site locations. This tiered approach to the evacuation helped to maintain continuous availability of all
support functions, as no time was lost because personnel was in transit. The transportation of support personnel was coordinated
by the Facilities Evacuation Team.
Back-up and Secure Information Systems
The Data Center Team immediately instituted the necessary back-up and protection of critical business applications and data. The
back-up of the entire day's activities was initiated and that information was available should the need arise to re-locate to the hotsite
facility. All systems and equipment were then secured to protect against any threat caused by the flooding and possible electrical
problems.
CHI/COR President Rick Effgen commented We were fortunate in many ways. We had sufficient warning time, sufficient
evacuation time, and the availability of all of our recovery teams. These factors, combined with extensive planning, allowed us to
practice what we preach. We were able to continue all major business functions during the crisis and return to full operations the
following business day.
The ramifications of this disaster, both physical and financial, will be felt throughout Chicago for a long time to come.
This article adapted from Vol. 5 #2.
DR World Main Index | Return to DRJ's Homepage
Disaster Recovery Worldİ 1999, and Disaster Recovery Journalİ
1999, are copyrighted by Systems Support, Inc. All rights reserved. Reproduction
in whole or part is prohibited without the express written permission form
Systems Support, Inc.